Phase Gates Served a Purpose. Good Agile Makes Them Unnecessary. 

Most med device teams I talk to have a version of the same story. The development work is “done,” but the release is still months away. Tests need to be formally documented. Documents need to be reviewed. Reviews need to be approved. And somewhere in that queue is the phase gate review where all of the work gets presented to stakeholders who are seeing most of it for the first time. 

At that point, the phase gate isn’t a control mechanism. It’s a reckoning. And unlike most reckonings, everyone in the room already knew it was coming. 

Why Phase Gates Exist 

Phase gates were created with a legitimate purpose: to provide visibility into where a project stood before committing to the next stage, to force communication between teams that never talked, and to create decision points for unengaged leaders. The problem isn’t the intent. The problem is that a gate placed at the end of development surfaces information too late, when it is most expensive to act on. 

The Rules Aren’t What You Think They Are 

One of the most persistent beliefs in the medical device industry is that the FDA requires a phase-gated, sequential development process. It doesn’t. The design control regulation requires that you be in control of your design (that inputs are defined, outputs are traceable, and verification and validation are performed) but it doesn’t specify the sequence in which those activities happen. Companies have created internal procedures that prescribe a linear process, and most team members don’t know if “this is what our SOPs require” or “this is what the FDA requires.” If you don’t like the rules, we have genuinely good news: since your organization made them, your organization can change them. 

What Agile Practices Replace 

Sprint reviews are probably the most valuable tool here. Instead of waiting for a gate review at the end of a phase, you present work to stakeholders after every sprint. Problems that would have been discovered at a gate in six months can now surface quickly. 

We saw exactly that happen with one medical device client. At their third sprint review, an important stakeholder saw the team’s priorities and stopped the meeting — the team was deep into work he considered far less critical than what was sitting at the bottom of the backlog. He resolved the confusion within two days, and the team pivoted. Under the old model, that discovery would have waited for the gate review. By that time several more sprints would have gone the wrong direction. The course correction would have required a steering committee, three approval layers, and a project manager updating a Gantt chart that nobody trusted anyway. 

A well-constructed Definition of Done also helps replace Phase Gates. When done means that testing, documentation, and approvals happened within the sprint, compliance work can’t be deferred. The same client cut their time from development completion to submission to roughly a third of what it had been. The V&V tail had been the variable that made every release date a guess. When each sprint closed with that work included, the tail shrank because most of it had already happened. 

Building This Understanding in Your Teams 

None of this happens automatically when you start running sprints. People at the team level need to understand not just what they’re supposed to do but why. That understanding doesn’t come from a mandatory annual compliance module that everyone clicks through and forgets. We’ve asked engineers and testers what they retain from that kind of training, and the honest answer is close to nothing. 

CARS for Teams is our answer to this problem: a one-day, instructor-led course for developers, testers, scrum masters, and other team members building FDA-regulated products. It covers what the design control regulations actually require, how AAMI TIR45 provides a roadmap for applying Agile within that framework, and how practices like the Definition of Done connect to those regulatory requirements. For organizations that want to extend the learning, we can break the course into shorter sessions with homework that sends participants back into their own QMS to identify specific procedures that conflict with agile delivery. 

The FDA never required you to separate development from quality. That was a choice embedded in procedures that can be changed. Reach out to us at info@agilityirl.com if you’d like to talk through where to start. 

— 

This post draws on conversations from the take5IRL podcast, including Episode 60 (Agile in a Regulated Environment), Episode 62 and 63 (Agile Medical Device: A Case Study, Parts 1 and 2), and Episode 83 (CARS for Teams). Listen at agilityirl.com or wherever you get your podcasts. 